Finishes

Furnishing-House Mother beds
Two wooden house mother beds have
been procured and stored.
They will soon be assembled in their specific rooms once the rooms have had the final painting
Water Harvesting
The four 2,000 liters tanks have all
been erected up on the roof top
and fully installed to receive and
distribute the running water into the
building.
The water is now fully
running into the main building
efficiently.

Additional 10.000 water tank has
been erected on the ground and
fully installed, tested to harvest the
rainwater.
Lightning Arrester installation
The work for lightning arrester is almost complete. Its pending work is the insulation and the clipping of the conductor against the wall all the way up to the top. It will be complete in the nest one week.
We are erecting a ladder to support the clipping of the conductor against the building wall.
Furniture for the school
we shall start making classroom chairs and tables on 1st September.
More furniture are yet to be procured. Some of the unprocured furniture include the following.
- The second dining table for the girls.
- The bunk beds for the girls
- The sofa sets for the girls lounge
- The tables for the classes
- The chairs for the classrooms
- Window blinders as well as the meshes.

Electricals-Wiring

There has been electrical work ongoing. This is the updates for the electrical work.
4th Floor:
All lights fixed, all switches fixed, all sockets fixed, all security rights fixed

3rd Floor:
All room lights fixed, all switches fixed, all sockets fixed, all security lights fixed.
2nd Floor:
All room lights fixed, all switches fixed, all sockets fixed, all security lights fixed. Pending work is on the girl’s kitchen cooker sockets
1st Floor:

All room lights fixed, all switches fixed, all sockets fixed, all security lights fixed.
The pending work is on the school kitchen cooker sockets and solar lights installation. all the pending electrical work is expected to be complete by the end of the first week of September.

Final Painting 4th Floor

The fourth floor has a total of 15 rooms and 4 washrooms. They include 7 classrooms, 5 bathrooms, 1 office, 1 laundry room and 1 drying area. Out of the 15 rooms of this floor 14 have been painted. only 1 room is pending so far. The unpainted room on this floor is an office. This office room will be painted among the last.
The picture above shows the staircase to the second floor from the ground floor.The ground floor painting is ongoing, and the photo here below shows the image of the multipurpose hall painting complete.
It is in this room where the beds for the house mother are kept waiting for the completion of the painting for their rooms.

Furnishing
Kitchen Cabinets and Shelves

The Ground/First floor kitchen cabinets and shelves are all complete. Also, the second-floor kitchen cabinets and the shelves are all complete
Beds:
Two beds for the 2 house mothers’ rooms are complete and a waiting for the final painting of the rooms before they are installed to the rooms.
Dining Table.:

We have procured one set of the dining table for the girls dining room. It is is placed in one of the ground floor rooms waiting for the final painting of the dining room.
Final Painting 3rd Floor

This floor has a total of 17 rooms. This includes 4 classrooms, 1 office for the Executive director, 9 toilets including washrooms for the girl’s wing, 1 mothers room and 3 girls rooms.
Out of the 17 rooms on this floor 12 rooms have been painted. only 5 are remaining. The remaining rooms include the office, mothers and girl’s room.
Final painting 2nd Floor

The second floor has a total of 14 rooms. The rooms include 4 classrooms, 1 sick bay, 9 toilets including the girls washroom. 1 mother and 1 girls rooms, 1girls kitchen 1 girls dining and 1 girls’ lounge.
Out of 14 rooms on this 2nd floor, 5 rooms are pending. the pending rooms include girls and mothers’ rooms, dining and lounge.
Final painting 1st Floor (ground)

The ground floor also has a couple of rooms. the total number of rooms for this floor are 17. They include 4 classrooms, 1 kitchen, 6 toilets, 2 offices, 1 store, 1 multipurpose hall, 1 security guard house and laundry machine room
out of the 16 rooms on the ground floor, 8 rooms are pending. it’s important to note that as of the day 29th August we have painted a total of 63 rooms 37 rooms have been painted and we are left with 26 rooms to go.
October – November 2025 finishes
The Sickbay Furnishing
The sick bay room is already furnished with the following: The crank bed for the sick. The bed is adjustable on the upper side of the head with its patient table on it. We have equipped the bed with a new mattress.
We have also bought a drip stand to be placed a alongside the bet to support with holding the drip in case of administration of treatment. We also procured a hard curtain to help with providing privacy in the room during examination and administration of treatment of a patent. The sick bay has also been equipped with an examination bed. The room has an installed hand washing basin with running water.


The Lounge
The lounge has been fully equipped with the chairs of the sofa to its capacity. The 2 sets we have had a capacity of 12 seats in a go. The lounge is looking so elegant and admirable. Alongside it is the dining room with two sets of dining tables with a total capacity of 12 seats.


The seats look so comfortable in the room. The colors of the seat are looking cool and are not easily able to reflect dirt. They complement very well the color of the room.
Bunk Beds
The Bedrooms for the girls have been equipped with new bank beds in each of the girls rooms. The beds have been installed in the rooms. Additionally, we have procured the new mattresses for each of the new beds. The beds are looking so nice . We will transition the girls into the new home fro the old home into the new beds and the new mattresses.
Dinning Seats
We bought 2 sets of modern dining tables with great colors and comfortability to provide a nice home environment and a home welcoming environment with the capacity to provide a socializing atmosphere. Each set of a rectangular table has a seating capacity of six members. The tables are made of durable wood simple made and very easy to clean.


House Mother Beds
The house mother’s rooms have been equipped too with the new beds. We have provided with single beds. Their rooms are self-contained with washrooms. The beds also have been laid with new mattresses and are now fully ready for occupation.

Blinders and Window Curtains
The blinders for the girls’ rooms have been installed. This helps with keeping privacy of the girls both day and night. We have installed the roller blinders on the side windows on the front side of the building.
The blinder allows the penetration of lights into the rooms and also make the room a pear cool. We have additionally installed the blinders on the offices and the sickbay, they add beauty and allow lights and fresh air to come in when adjusted accordingly.
The back windows of the girls’ bedrooms have had the curtains installed windows and the curtains on the back side windows of the building



Mosquito window nets installations.
We have installed the meshed windows that prevents the mosquitos from coming through into the rooms. The installations have been made to the two floors of the girl’s rooms including their kitchen room.


Class room chairs and table progress.
As was planned we are in progress with the installation of the classroom chairs and tables. By December 15th we shall have reached our target on the number of class chairs and tables and classes will almost be ready for visiting by the parents. We have also procured classroom chairs for the kindergarten. The classrooms that have been furnished are looking great.